Press Release
Sumitomo Electric Completes HVDC Cable Projects in Europe & Japan
May 16, 2019
Sumitomo Electric Industries, Ltd.
Sumitomo Electric Industries, Ltd. is pleased to announce the completion of two high-voltage direct current (HVDC) interconnector cable projects using crosslinked polyethylene (XLPE) insulated cables:
With the increasing capacity of renewable energy sources and the necessity of long-distance power interconnectors for efficient use of such renewable energy between countries and regions, HVDC cable technology, which is suitable for long-distance power transmission, has been gaining significant attention in international markets.
In support of this trend, Sumitomo Electric has recently completed the construction of a 400-kV HVDC XLPE cable system, the highest voltage in the world for an HVDC-XLPE cable system, for NEMO Link, which connects the UK and Belgium.
Sumitomo Electric has also completed construction of the Hokuto-Imabetsu HVDC Link with 250-kV HVDC XLPE cable, which will increase transmission capacity between Honshu (Japan's main island) and Hokkaido (Japan's northern island) along with the existing circuit for the Hokkaido-Honshu DC Interconnector that commenced commercial operation in 2012. The route length of this HVDC cable system is the longest in the world for an inter-strait tunnel.
In addition to these recently-completed HVDC projects, Sumitomo Electric is currently constructing the first HVDC cable system in India. Sumitomo Electric will continue its endeavour to lead the global market by utilizing the Company's state-of-the-art HVDC cable technologies and experience in large-scale projects.
Construction of 400-kV HVDC XLPE cable system connecting the UK and Belgium
In Europe, with the aim of achieving efficient use of energy and security of energy supply, electricity interconnectors connecting countries are playing significant roles. NEMO Link, a joint venture between National Grid in the UK and ELIA in Belgium, initiated a project to connect Kent in the UK and Zeebrugge in Belgium with an HVDC cable system. Sumitomo Electric secured an Engineering, Procurement and Construction (EPC) contract for the interconnector project in June 2015.
This project was the first in the world to adopt 400-kV DC XLPE insulated cable.*2 Production and installation of the cable system was completed in December 2018, and since the end of January 2019 the system has been in commercial operation. In April 2019, Sumitomo Electric announced that all necessary procedures toward completion of the project have finished. The commencement of operation of the system marks the successful installation of the world's first 400-kV HVDC XLPE cable system.
Project outline
Transmission capacity | 1,000MW |
---|---|
Total route extension | 141.5km (submarine:130km, land:11.5km) |
Type of transmission line | Cable (no OHL) |
AC-DC conversion | Voltage-sourced convertor (VSC) |
Pole structure | Symmetrical monopole |
Installation of the 250-kV HVDC XLPE cable system for a new Hokuto-Imabetsu HVDC Link
To secure a stable power supply between Hokkaido and Honshu , HEPCO has constructed the new Hokuto-Imabetsu HVDC Link (300 MW), connecting Hokuto Converter Station in Hokkaido and Imabetsu Converter Station in Honshu, in addition to the existing Hokkaido-Honshu Interconnection Line. The commercial operation started on March 28, 2019, increasing the total transmission capacity between Hokkaido and Honshu from 600 MW to 900 MW.
This interconnector features voltage-sourced converters (VSC) and cable installation in the Seikan Tunnel (a subsea railway tunnel). Among 122 km of overall transmission line, Sumitomo Electric supplied and installed about 24 km of 250-kV HVDC XLPE cables, which were connected to the overhead transmission lines that were also supplied by the Company at both onshore ends. Although there were challenging situations during cable installation inside the subsea tunnel, Sumitomo Electric delivered the system on time. This HVDC cable system is the longest in the world for a strait tunnel. For the HVDC link, Sumitomo Electric also supplied 98 km of overhead conductors and provided technical support for the overall transmission line installation.
Project outline
Transmission capacity | 300MW |
---|---|
Route extension | 122km(24km in subsea tunnel, 98km outside of tunnel) |
Installation route | In the Seikan Tunnel |
AC-DC conversion | Voltage-sourced convertor (VSC) |
Pole structure | Asymmetric monopole |
- The leading company for high voltage cable and overhead conductor:
https://global-sei.com/power-cable-business/ - Press release, June 8, 2015:
"J-Power Systems Wins Contract with NEMO LINK for HVDC Subsea Interconnector Cable System between UK and Belgium"
https://global-sei.com/company/press/2015/06/prs044.html - Press release, March 27, 2017:
"Siemens and Sumitomo Electric win order for HVDC link and agree on cooperation"
https://global-sei.com/company/press/2017/prs031.pdf - Sumitomo Electric Group e-magazine id, July 2017:
"International Submarine Cable Project: Installing the world's highest voltage DC XLPE insulated cable across the English Channel"
https://global-sei.com/id/2017/07/project/index.html - Sumitomo Electric Group e-magazine id, July 2017:
"Contribution to Stable Interregional Electricity Supply"
https://global-sei.com/id/2017/07/quarterly/file001.html